Milestone
Start date
Freeze date
Delivery date
MVP concept
Ongoing
31 May
7 June
Visual styleguide
3 June
7 June
14 June
User stories
30 May
7 June
7 June
Product design
7 June
19 July
2 August
Engineering
7 June
4 October
9 October
Internal launch and bug fixes
10 October
29 November
Client on-boarding
2 December
19 December
Launch
23 December
27 December